Interconnection Standards

May 29, 2024

Summary

In December 2005 the Colorado Public Utilities Commission (PUC) adopted standards for net metering and interconnection, as required by Amendment 37, a renewable energy ballot initiative approved by Colorado voters in November 2004. The interconnection rules were overhauled in July 2021.

The PUC standards generally apply to investor-owned utilities (IOUs) with 40,000 or more customers and all electric cooperatives. Municipal utilities with 5,000 customers or more are required to adopt interconnection rules that are functionally similar to the PUC's standards (see H.B. 08-1160). Electric cooperatives and municipal utilities may reduce or waive any insurance requirements that apply to IOUs.

Colorado’s interconnection rules are based on the Federal Energy Regulatory Commission’s (FERC) interconnection standards for small generators, adopted in May 2005 by FERC Order 2006. Colorado's rules for interconnection include requirements, standards, and review procedures for three levels of interconnection for systems up to 10 megawatts (MW), based on system complexity.

Level 1 Interconnection

Level 1 interconnection applies to inverter-based systems with a maximum nameplate capacity of 25 kilowatts-AC; these systems can be paired with energy storage systems no larger than 25 kW-AC. These systems must comply with the IEEE 1547 and UL 1741 standards and other applicable standards.

Level 2 Interconnection

Level 2 interconnection is the fast track process, and eligible systems depend on the line voltage, system size, and system location in relation to the utility line:

Line Voltage Eligibility Regardless of LocationEligibility Meeting Location Requirements
< 5 kV ≤ 500 kW ≤ 500 kW
≥ 5 kV and 15 kV ≤ 2 MW ≤ 3 MW
≥ 15 kV and 30 kV ≤ 3 MW ≤ 4 MW
≥ 30 kV and < 69 kV ≤ 4 MW ≤ 5 MW

To meet the location requirements, inverter-based systems must be within 2.5 electrical circuit miles of a substation and on a mainline. All synchronous and induction facilities have a maximum size of 2 MW, regardless of location, for Level 2 eligibility.

These systems must comply with the IEEE 1547 and UL 1741 standards and must be connected to a portion of the distribution system that is subject to the utility's tariff. There are specific limitations on a single system's potential impact and the aggregate potential impact on the grid. If a proposed interconnection fails one of the various screening tests, the customer-generator may need to pay for a supplemental review by the utility.

Level 3 Interconnection

Level 3 interconnection applies to systems up to 10 MW that do not qualify for either Level 1 or Level 2 interconnection procedures. Level 3 interconnection may require studies involving project scope, feasibility, system impact, and facilities. The customer may need to make a deposit and incur a portion of the total costs associated with these studies. Insurance levels will be determined on a case-by-case basis by the servicing utility.

Liability Insurance

A utility can only require an applicant to purchase insurance covering utility damages in the following amounts for each occurrence:

  • $3 million per occurrence for non-inverter-based systems over 5 MW
  • $2 million per occurrence for inverter-based systems over 5 MW and non-inverter-based systems between 2-5 MW
  • $1 million per occurrence for inverter-based systems between 1-5 MW and non-inverter-based systems between 500 kW-2 MW
  • $500,000 per occurrence for non-inverter-based systems between 50-500 kW
  • No insurance is required for inverter-based systems under 1 MW and non-inverter-based systems under 50 kW

Program Overview

Implementing Sector: State
Category: Regulatory Policy
State: Colorado
Incentive Type: Interconnection
Web Site:
Administrator:
Start Date:
Eligible Renewable/Other Technologies:
  • Geothermal Electric
  • Solar Thermal Electric
  • Solar Photovoltaics
  • Wind (All)
  • Biomass
  • Hydroelectric
  • Combined Heat & Power
  • Landfill Gas
  • Wind (Small)
  • Anaerobic Digestion
  • Fuel Cells using Renewable Fuels
  • Other Distributed Generation Technologies
  • Microturbines
  • Lithium-ion
Applicable Utilities: IOUs with 40,000 or more customers
All electrical cooperatives
Municipal utilities with 5,000 or more customers
System Capacity Limit: 10 MW
Standard Agreement: Yes
Insurance Requirements: None (up to 50 kW, non-inverter / up to 1 MW, inverter)
$500,000 (50-500 kW, non-inverter)
$1,000,000 (500 kW-2 MW, non-inverter / 1-5 MW, inverter)
$2,000,000 (2-5 MW, non-inverter / 5+ MW, inverter)
$3,000,000 (5+ MW, non-inverter)
Net Metering Required: No

Authorities

Name: 4 CCR 723-3, Rule 3850 et seq.
Date Enacted: 12/15/2005
Effective Date: 7/2/2006
Name: C.R.S. 40-9.5-118
Name: C.R.S. 40-2-124
Date Enacted: 3/26/2008

Contact

Name: Colorado Public Utilities Commission
Organization: Colorado Public Utilities Commission
Address: 1560 Broadway, Suite 250
Denver CO 80202
Phone: (303) 894-2000
Email: dora_puc_website@state.co.us

This information is sourced from DSIRE; the most comprehensive source of information on incentives and policies that support renewables and energy efficiency in the United States. Established in 1995, DSIRE is operated by the N.C. Clean Energy Technology Center at N.C. State University.