Summary

The Louisiana Public Service Commission (PSC) adopted rules for net metering and interconnection in November 2005. Louisiana's rules, based on those in place in Arkansas, require publicly-owned utilities and rural electric cooperatives to offer net metering to customers with systems that generate electricity using solar, wind, hydropower, geothermal or biomass resources.* Fuel cells and microturbines that generate electricity entirely derived from renewable resources are also eligible. The rules apply to residential facilities with a maximum capacity of 25 kilowatts (kW) and commercial systems with a maximum capacity of 300 kW.

Utilities must provide customers with a meter capable of measuring the flow of electricity in both directions. Although utilities must pay for the cost of the meter itself, customer-generators must pay a one-time charge to cover the installation cost of the meter. Interconnected systems must meet all safety and performance standards established by local and national electric codes, including the National Electric Code (NEC), the Institute of Electrical and Electronics Engineers (IEEE), the National Electrical Safety Code (NESC), and Underwriters Laboratories (UL). A manual external disconnect switch is required for all interconnected systems. The manual external disconnect switch requirement is waived if the inverter is designed to shut down if utility service is lost, the inverter is warranted by the manufacturer to shut down in this situation, and the inverter has been inspected and tested by utility personnel.

Customers seeking to interconnect and net meter must submit an interconnection agreement to a utility 45 days before interconnection. Utilities must use a PSC-approved standard interconnection agreement for interconnected facilities.

Customers must pay for "interconnection costs," defined as "the reasonable costs of connection, switching, metering, transmission, distribution, safety provisions and administrative costs incurred by the electric utility directly related to the installation and maintenance of the physical facilities necessary to permit interconnected operations with a net-metering facility, to the extent the costs are in excess of the corresponding costs which the electric utility would have incurred if it had not engaged in interconnected operations, but instead generated an equivalent amount of electric energy itself or purchased an equivalent amount of electric energy or capacity from other sources." Furthermore, following notice and opportunity for public comment, the PSC may authorize a utility to assess customer-generators "a greater fee or customer charge, of any type, if the electric utility's direct costs of interconnection and administration of net metering outweigh the distribution system, environmental and public-policy benefits of allocating the costs among the electric utility's entire customer base."

*The PSC regulates investor-owned utilities and electric cooperatives in Louisiana; it does not regulate municipal-owned utilities, and its rules do not apply to municipal utilities. Municipal utilities must develop their programs based on the statute.

Program Overview

Implementing Sector: State
Category: Regulatory Policy
State: Louisiana
Incentive Type: Interconnection
Web Site: https://www.lpsc.louisiana.gov/Utilities_NetMetering
Administrator:
Start Date:
Eligible Renewable/Other Technologies:
  • Geothermal Electric
  • Solar Photovoltaics
  • Wind (All)
  • Biomass
  • Hydroelectric
  • Wind (Small)
  • Fuel Cells using Renewable Fuels
  • Microturbines
Applicable Utilities: All utilities
System Capacity Limit: Commercial and agricultural: 300 kW
Residential: 25 kW
Standard Agreement: Yes
Insurance Requirements: Not addressed
External Disconnect Switch: Not required for certain inverter-based systems; required for all other systems
Net Metering Required: Yes

Authorities

Name: La. R.S. 51:3061 et seq.
Date Enacted: 6/27/2003
Effective Date: 10/1/2003
Name: Net Metering Rules

Contact

Name: Public Information
Organization: Louisiana Public Service Commission
Address: 602 North Fifth Street
Baton Rouge LA 70821-9154
Phone: (225) 342-4404

This information is sourced from DSIRE; the most comprehensive source of information on incentives and policies that support renewables and energy efficiency in the United States. Established in 1995, DSIRE is operated by the N.C. Clean Energy Technology Center at N.C. State University.