Washington City Power - Net Metering

May 31, 2017

Summary

Washington City adopted a net metering program, including interconnection procedures, in January 2008, and updated the policy in December 2014.* Net metering is available to any customer of Washington City Electric that generates electricity using solar, wind, or other City-approved renewable energy resources. Systems up to 10 kW in capacity are allowed to connect to the City distribution system. 

At the customer's expense, the municipal utility will provide a single, bidirectional meter to measure the in-flow and out-flow of electricity at the customer's home. Systems are restricted to being sized to provide no more than 120% of the historic maximum monthly energy consumption of the customer. Customers receive credit at the wholesale rate (4 cents per kWh) for any net excess generation (NEG) at the end of a billing period. The utility takes ownership of all renewable energy credits (RECs) and other renewable attributes associated with customer generation. 

Net-metered systems must comply with the IEEE 1547 and UL 1741 technical standards, where applicable, and must be certified by the utility. The customer must install a manual disconnect switch. Washington City will inspect installations prior to interconnection. Washington City also maintains the right to inspect a customer's system anytime after the initial approval during reasonable hours and with reasonable prior notice. If the city finds the system to be in non-compliance, the city may require the system to be disconnected until compliance is achieved. 

Washington City has also set an aggregate capacity limit of 500 kW of renewable resources allowed to connect to the City distribution system. The City will not take further applications for connection once this cap is reached.  




* Utah enacted legislation in 2002 requiring all investor-owned electric utilities and cooperative utilities to offer net metering to their customers. However, the law does not apply to municipal utilities. Washington City offers net metering voluntarily.

Program Overview

Implementing Sector: Utility
Category: Regulatory Policy
State: Utah
Incentive Type: Net Metering
Web Site: https://washingtoncity.org/services/power/EnvironmentallyFriendly/NetMetering
Administrator:
Start Date:
Eligible Renewable/Other Technologies:
  • Solar Photovoltaics
  • Wind (All)
  • Wind (Small)
Applicable Utilities: Washington City
System Capacity Limit: 10 kW
Aggregate Capacity Limit: 500 kW
Net Excess Generation: Reconciled monthly at wholesale power rate
Ownership of Renewable Energy Credits: Utility owns RECs
Meter Aggregation: Not allowed

Authorities

Name: Ordinance No. 2014-34

Contact

Name: Jessica Black
Organization: Washington City
Address: 111 N. 100 E
Washington UT 84780
Phone: (435) 656-6329
Email: jblack@washingtoncity.org
Name: Kelly Carlson
Organization: Washington City
Address: 111 N. 100 E
Washington UT 84780
Phone: (435) 656-6320
Email: kcarlson@washingtoncity.org

This information is sourced from DSIRE; the most comprehensive source of information on incentives and policies that support renewables and energy efficiency in the United States. Established in 1995, DSIRE is operated by the N.C. Clean Energy Technology Center at N.C. State University.